Assembly of carbon dust silos

… in the power plant “Schwarze Pumpe” 2006

Assembly of two carbon dust silos

Client:                                  AJO – tec GmbH
Construction site:             Power plant “Schwarze Pumpe”
Period of assembly:         April until August 2006


The silos with an aperture of 8,00m and a height of 21,00m were pre-assembled out of segments at the construction site.       
The lifting of the 50,0 to. heavy silos was carried out via a 300 to. truck-mounted crane.       
The welding was predominantly executed by the rod welding process.