Cooling pipe with pillowplates

For a research institute In 2026 we worked with pillowplates for the first time. The pipe was designed for a research and development institute and has a diameter of 750mm and a length of 4,6m. The weight is approximately 1,5 to. The pipe is without any pressure and made of 1.4571 (316Ti) while the pillows […]

Manufacturing and assembly of two storagetanks

with 2,9 to 3,2 to 16m they don’t just seem to be huge, they are! In 2025 we designed and manufactured two storagetanks according to EN13445 and later installed them on site. They have a diameter of 2,9m and a length of 16m. We manufacured these tanks without saddles because the saddles of the old […]

Partial renewal of a drying drum

 In 2024 we had a job for a partial renewal of a drying drum with a diameter of 3,4m and a length of approximately 8m to be renewed. The new part that was deliveredhad a total weight of 45,5 to. Due to the available space on site the new part needed to be delivered in […]

Manufacuring and Erection of special apparatus

… appx. 18m long, width of 2,9m and 3,7m height In 2024 we manufacutred a special apparatus for dissolving of salt for our customer K+S at his location in Philippsthal. The apparatus had a length of approximately 18m, was manufacutred in eight parts and had a total weight of 60 tons. Due to the circumstanced […]

Production of two storage containers

zurzeit kein Bild vorhanden

… each approx. ø3m x approx. 9.6m In 2023, we manufactured two tanks including a walk-on platform for the company K-Ley GmbH & Co. The containers each had a diameter of approx. 3m and a length of approx. 9.6m. The containers were manufactured by us to be rubberized and completely pre-assembled for adjustment of the […]

Renewal of an extraction system

… over a length of approx. 370m In 2023, we planned, manufactured and installed the extraction pipeline for a Möller building for the steelworks in Salzgitter. The pipeline has diameters from DN150 to DN1400 and extends over a length of approx. 370m. Due to the rerouting of various pipe strings, we were supported here by […]

Stirring vessel for Wintershall

approx. ø3.2m x approx. 5.6m In 2022, we manufactured and installed an agitator vessel for the K+S site “Wintershall” (in Heringen). The vessel has a diameter of approx. 3.2m and a length of approx. 5.6m. Due to the space available during assembly, it was not possible to deliver it ready for installation, so the agitator […]

Crystalliser for Wintershall

ø2.6m x approx. 11.2m In 2022, we manufactured and installed a crystallizer for the K+S site “Wintershall” (in Heringen). The apparatus has a diameter of approx. 2.6m and a length of approx. 11.2m. Due to the space available during assembly, it was not possible to deliver the crystallizer in a ready-to-install state, so it was […]

Pipeline installation for K+S

approx. 640m pipeline DN250 In 2021, we delivered and installed an approx. 640m long steel pipeline for the K+S site “Hattorf” (in Philippsthal). The pipeline has a diameter of 273mm and a wall thickness of 10mm. The pipeline was only connected with flanges in a few places and therefore had to be welded on site […]

Partial renewal of a drying drum

ø3.4 x 8.7m incl. assembly In 2021, we manufactured and installed a drum piece for the partial renewal of a dryer drum for the K+S site “Hattorf” (in Philippsthal). The drum has a diameter of approx. 3.4m and was renewed over a length of approx. 8.7m. Due to its dimensions, it was not possible to […]