Installation of a steel converter

… Replacement Converter in Salzgitter 2007 In the plant Salzgitter of the client Salzgitter Flachstahl GmbHPeriod of assembly: January 2007 until March 2007Plant shutdown 21 days for container replacementContractor SMS DEMAG Approx. 6 weeks pre-assembly in Salzgitter, replacement of entire vessel in 21 days stagnancy, unit weight approx. 330 to., fabrication and utilization of a […]
Assembly of a weir barrel

… in Wieblingen near Heidelberg, 2008 WSM replaced the weir barrel in Wieblingen in the year 2008. The reconstructions were carried out with 10 workers within 14 days.
Flood gate exchange Bamberg

… Replacement of Floodgates 2010 in Bamberg By the long lasting employment during assembly of equipment in varying domains, our technical staff comes with secured know-how at repairs and reconstruction of machinery and systems, e.g. at steel-water-works.In march/april 2010 the sluice in Bamberg was equipped with new gates on behalf of and lead-managed by the […]