Installation of 5 tandem trestles
… in Linz, Austria 2007
Assembly of a KONTI TANDEM cold roll installation in plant VA Stahl in Linz, Austria.
Contractor VAI Voestalpine Linz, Austria
Period of assembly: June 2006 until March 2007, including commissioning Accomplishment of assembly in collaboration with a parter
WSM assembled the core piece, the five cold roll trestles, unit weight of the roll housing approximately 95,0 to.
Assembly of the subsurface tape guide with 90° redirection via a turnabout roll
Realization of the installation site was carried out parallel to the assembly of the galvanizing plant FVZ4 (SUNDWIG) and an inspection line ISL5.
80 assemblers were applied during the peak of the multishifted day-to-day running of the work site
The overall weight of the mounted mechanis was approximately 1.300 to.
The adjustment specifications at the roll housings of our client was +- 0,05mm/m, in axial und horizontal direction.