Renewal of an extraction system
… over a length of approx. 370m
In 2023, we planned, manufactured and installed the extraction pipeline for a Möller building for the steelworks in Salzgitter. The pipeline has diameters from DN150 to DN1400 and extends over a length of approx. 370m. Due to the rerouting of various pipe strings, we were supported here by an external planner specializing in pipelines. The subsequent production took approximately 36 weeks. The assembly on site took place in 12 weeks during the shutdown period specified by the plant.
The total package comprised around 80 tons, consisting in roughly equal parts of normal steel S235 Hardox500 and corrosion-resistant steel 1.4571.
Year: 2023
Total tonnage: 80 tons