WSM MESSER Spezialmontagen GmbH

Steelworks

Installation of 5 tandem trestles
… in Linz, Austria 2007 Assembly of a KONTI TANDEM cold roll installation in plant VA Stahl in Linz, Austria.Contractor VAI Voestalpine Linz, Austria Period

Installation of a new exhaust gas line
… in the HKM plant in Duisburg 2001 Assembly of an exhaust gas line in the sinterplant at HKM Hüttenwerke Krupp Mannesmann in Duisburg, project

Installation of a steel converter
… in Salzgitter 2007 In the plant Salzgitter of the client Salzgitter Flachstahl GmbHPeriod of assembly: January 2007 until March 2007Plant shutdown 21 days for

Assembly of 3 slag silos
… in Salzgitter 2007 Period of assembly: October 2005 until May 2006Contractor Paul Wurth Umwelttechnik, Essen Construction of a new furnace slag granulation plant.3 silos,

Installation of the secondary dust removal system
… in Eisenhüttenstadt 2007 Assembly of a secondary dust removal system of the converter A and B at EKO Eisenhüttenstadt in the year 2007 Period

Installation of a new galvanizing plant
… in Linz, Austria 2007 nstallation of the galvanizing plant FVZ4 in the factory of VA Stahl in Linz, AustriaClient SUNDWIG GmbHPeriod of assembly: May