Installation of a new galvanizing plant
… in Linz, Austria 2007 nstallation of the galvanizing plant FVZ4 in the factory of VA Stahl in Linz, AustriaClient SUNDWIG GmbHPeriod of assembly: May 2006 until January 2007, including commissioningAssembly of the mechanics approximately 2.000 to. additionally the loop memory for the company KLAAS SIEMENS approximatly 400 to. steelworkInstallation works in day- and night […]
Installation of the secondary dust removal system
… in Eisenhüttenstadt 2007 Assembly of a secondary dust removal system of the converter A and B at EKO Eisenhüttenstadt in the year 2007 Period of assembly: July 2007 until December 2007Contractor EKO EisenhüttenstadtOverall weight of the installation parts approximately 1.000 to.
Assembly of 3 slag silos
… in Salzgitter 2007 Period of assembly: October 2005 until May 2006Contractor Paul Wurth Umwelttechnik, Essen Construction of a new furnace slag granulation plant.3 silos, unit weight approximately 350 to., 500 to. steel construction, 1 granulation tower weighs approximately 300 to. Pre-assembly of the silos compared to the installation area out of single componentsLifting of […]
Installation of a steel converter
… in Salzgitter 2007 In the plant Salzgitter of the client Salzgitter Flachstahl GmbHPeriod of assembly: January 2007 until March 2007Plant shutdown 21 days for container replacementContractor SMS DEMAG In the plant Salzgitter of the client Salzgitter Flachstahl GmbHPeriod of assembly: January 2007 until March 2007Plant shutdown 21 days for container replacementContractor SMS DEMAG Approx. […]
Installation of a new exhaust gas line
… in the HKM plant in Duisburg 2001 Assembly of an exhaust gas line in the sinterplant at HKM Hüttenwerke Krupp Mannesmann in Duisburg, project HKM Leep Period of assembly: September 2001 until March 2002.Contractor Hüttenwerke Krupp Mannesmann DuisburgPipe diameter DN 4.500mm
Installation of 5 tandem trestles
… in Linz, Austria 2007 Assembly of a KONTI TANDEM cold roll installation in plant VA Stahl in Linz, Austria.Contractor VAI Voestalpine Linz, Austria Period of assembly: June 2006 until March 2007, including commissioning Accomplishment of assembly in collaboration with a parterWSM assembled the core piece, the five cold roll trestles, unit weight of the […]